Hello,

In my planning I have defined one resource called HW which I have defined as as cost resource.
I want to use this to log cost for some HW equipments.
So on some task I assigned this HW resource and give it the value of my equipments.
This price is correctly taken into the task cost.

Problem is that when I fill my progress this HW value is never added into the task real cost and so even when I define my task as 100% done I still have a remaining cost on this task with this value.
Have I done something wrong ?

Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Cost resource not taken in real cost [Project 2013] More accuracy with resource, unit %, and cost? cag8f Project 18 01-02-2016 01:51 PM
Cost resource not taken in real cost Cost Reporting 2013 Steve. Project 7 05-14-2014 06:28 AM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
How to rename cost column ketanco Project 3 06-15-2012 03:06 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:16 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft