#1
|
|||
|
|||
![]() You'll need to record the actual cost for the Hardware. Split your screen to show the task form - and when the task is 100% complete - enter the actual hardware costs in the task form formatted to show cost. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
cag8f | Project | 18 | 01-02-2016 01:51 PM |
![]() |
Steve. | Project | 7 | 05-14-2014 06:28 AM |
Portfolio Analyzer Cube - Cost Resource Question | seanpears99 | Project | 2 | 03-07-2013 06:59 PM |
How to rename cost column | ketanco | Project | 3 | 06-15-2012 03:06 PM |
entering values for a cost type resource | ketanco | Project | 3 | 12-26-2011 09:25 AM |