We are producing a Gantt chart for a project.
The project is set to Start 06/03/2017 So week 1 in our heads is obviously week commencing 06/03/2017 However some prep work needs done 8 weeks before the project starts in earnest So we have a task 1a that starts 6 weeks prior to 06/03/2017 eg 09/01/2017 When I add this task the weeks are renumbered so that that week 1 starts when Task 1a starts (09/01/2017) rather than what the project start date is set to (06/03/2017). However when you preview/print it week 1 is indeed as per the project start date (06/03/201) and task1a is shown to run from -8w to week1 Project 2007 doesn't display this behaviour. On screen shows W1 as being 6/3/2017 and the print/preview matches. The issues is for Project 2013 and have been tried on 3 or 4 machines all displaying the same issue. How do we get the Gantt chart to match the print preview/printout. I've attached 2 images. One is a screen shot from within Project The other is a screen shot after having printed the doc to PDF - however the physical print out matches this. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
survivo01 | Word | 4 | 05-22-2014 12:57 AM |
![]() |
sprout | Word | 7 | 08-05-2013 12:40 PM |
![]() |
terik222 | Word | 3 | 03-27-2013 02:43 PM |
![]() |
Jamal NUMAN | Word | 7 | 05-05-2011 01:30 AM |
![]() |
anthrax19888 | Word | 1 | 10-12-2009 08:09 AM |