Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 07-17-2015, 02:10 AM
pascalbidouille pascalbidouille is offline EVM on summary tasks Windows 7 64bit EVM on summary tasks Office 2013
Novice
EVM on summary tasks
 
Join Date: Jun 2015
Posts: 18
pascalbidouille is on a distinguished road
Unhappy EVM on summary tasks

Hello,

I have some problem with the calculation of Earned value on summary tasks.
When I fill the %work done in a normal task : no problem EV is calculated, no problem.
But I have some resources that I have affected to a summary task.
In this case, I have the correct %work done calculated for my summary task based on sub tasks.
Bu EV for the summary task is calculated as SUM of EV from sub tasks and not as %work x Planned Value.
I thus get a Cost Variation between real cost and earned value.
Here is a screen shot of a small example :
(Sorry my MS Project version is in french so :
VA = EV
VC = CV
VP = PV


%travail = % work)

Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
EVM on summary tasks How do you create a Summary report of all 1N pages/tasks rduram OneNote 1 05-25-2015 04:22 AM
EVM on summary tasks Calculation of Percentage Completion of Summary Tasks raminraiszadeh Project 2 04-06-2015 06:38 AM
Automatic calculation of summary tasks Puddlerunna Project 1 10-15-2014 03:09 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
EVM on summary tasks Creating Report based on 'Task Summary' and 'Sub Tasks' alijahed Project 1 02-01-2013 04:20 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft