#1
|
|||
|
|||
![]()
Hello,
Can you please tell me the exact formula that MS Project uses when it calculates the percentage completion of summary tasks? Thank you |
#2
|
|||
|
|||
![]()
Please disregard... I found the answer.
|
#3
|
|||
|
|||
![]()
http://support.microsoft.com/en-us/kb/101495
It references older versions of Project but still applies. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
Automatic calculation of summary tasks | Puddlerunna | Project | 1 | 10-15-2014 03:09 AM |
Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
![]() |
alijahed | Project | 1 | 02-01-2013 04:20 AM |
![]() |
MarcelaTeich | Project | 13 | 03-14-2012 08:41 AM |