  #3  
Old 04-27-2015, 03:09 PM
JulieS JulieS is offline Team Planner view with 0% assignment Windows 7 64bit Team Planner view with 0% assignment Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Resources assigned to tasks with zero percent assignment units does not calculate work. My guess is, that is why they do not show the assignment in the Team Planner view.

Why do you have resources assigned at 0% assignment unit? The assignment does show in the Resource Usage view.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Team Planner view with 0% assignment Why do my Resources have different Project Start Dates in Team Planner ? AmmeLane Project 1 06-06-2014 06:42 AM
Team Planner view with 0% assignment Formatting External Tasks in Team Planner steve086 Project 3 01-10-2014 03:11 PM
Refining Team Planner View in MS Project 2010 CarolinaGamecock Project 1 11-27-2013 12:18 PM
Team Planner view with 0% assignment How to Improve task Detail in Team Planner ? Tray Project 9 07-07-2013 03:44 PM
Team Planner view with 0% assignment Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft