![]() I noticed that after playing around for a while with my schedule, I'm stuck with a dotted line in front of a task on the Gantt chart. And I just can't get rid of it. You know like when you level a task and in breaks it into pieces and that, at any time after, you can decide to drag them back together? Well, in this case, if I select the block and try to drag it back over the dotted line, the dotted line follows with it so can't get rid of it. Grrrrrrrr! |
#2
|
|||
|
|||
![]()
Take a look at the Task Usage view. Do you have resources assigned with zero work showing in the beginning of the task? Does the resource assignment have a different start date than the task?
|
#3
|
|||
|
|||
![]()
You were right about the zeroes!!!!
|
#4
|
|||
|
|||
![]()
Great. Glad it was a fairly easy fix. Thanks for the feedback.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Straitsfan | Word | 1 | 11-11-2013 11:55 AM |
How do I lose these dotted lines? | jlumbtx | Word | 4 | 11-09-2013 10:29 PM |
![]() |
smalano | Word | 4 | 04-08-2013 04:14 AM |
![]() |
btdaniel | Word | 1 | 05-21-2012 08:00 AM |
![]() |
rolla1 | Word | 1 | 12-22-2009 05:25 AM |