View Single Post
 
Old 04-22-2015, 02:04 PM
patrickd123 patrickd123 is offline Windows XP Office 2003
Novice
 
Join Date: Dec 2011
Posts: 21
patrickd123 is on a distinguished road
Default What about this dotted line at the beginning of a task?

I noticed that after playing around for a while with my schedule, I'm stuck with a dotted line in front of a task on the Gantt chart. And I just can't get rid of it. You know like when you level a task and in breaks it into pieces and that, at any time after, you can decide to drag them back together? Well, in this case, if I select the block and try to drag it back over the dotted line, the dotted line follows with it so can't get rid of it. Grrrrrrrr!
Reply With Quote