![]() |
#1
|
|||
|
|||
![]()
Hello
we have tried to set the Start and Finish into Start1 and Finish1 using the Project set interim baseline function. But this does not appear to be working, what is happening is that the Start is being copied into Finish 1? Can you please advise what might be happening here, we are using MS Project 2013 |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Finding Earned Values for Different Baselines in a single project | pratik6312 | Project | 1 | 08-22-2013 11:18 AM |
![]() |
ketanco | Project | 1 | 02-08-2012 02:20 PM |
![]() |
poyns | Project | 1 | 05-27-2010 10:59 AM |