Hi

Welcome to the forum.

My suggestion would be to create two separate tasks linked to each other with a Predecessor.

You cannot assign Predecessors to "parts" of a split task.

Hope this helps.

Tony
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Splitting Tasks - Predecessors Multiple predecessors mrgipponi Project 3 09-01-2014 11:38 AM
Splitting Tasks - Predecessors Splitting Out PDFs 4mysanity Word VBA 27 12-05-2012 03:31 PM
Splitting Tasks - Predecessors Task Indicator - All predecessors complete true/false, y/n jdove78 Project 2 10-10-2012 05:53 PM
Document splitting MsLavigne Word 2 05-09-2012 05:52 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft