Hi everyone, first time poster.
I am new to Project and and still trying to learn the ropes. Sorry if my question has a simple solution but I cant for the life of me find it anywhere.
So say I have 3 tasks (Task 1, Task 2, Task 3).
Task 3 will take 10 days for completion, split into 6 days(Part 1) and 4 days(Part 2).
Part 1 is dependent on Task 1 being completed and Part 2 is dependent on Task 2 being completed.
My question is how do you assign predecessors to split tasks, so that Part 2 begins when Task 2 is finshed.
Thank You!