cag8f cag8f is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 7 64bit [Project 2013] More accuracy with resource, unit %, and cost? Office 2013
Novice
[Project 2013] More accuracy with resource, unit %, and cost?
 
Join Date: Jan 2015
Posts: 7
cag8f is on a distinguished road
Default

Thanks for the very informative reply. It did the trick! But...again for some reason I wasn't completely up-front with what I am trying accomplish. Here is what I'm trying to do. I have a task that will take 2 hours of my employee's time, but will take 2 weeks to complete (since my client has to review/send comments/etc). In MS Project, I would like to track the 2 hours my employee works (including costs), as well as track the 2 week duration, for scheduling purposes.

Here is what I have done, and the issue I am encountering. I have added my employee to the project as a resource. I have also added the task in-question, at a duration of 2 weeks. Per your instructions, I allocated 2 hours of my employee to this task without issue. But my issue arises when I try to add a second similar task. This second task is identical to the first (duration, resource allocation, etc), except for a different task name. When I add this second task, I am met with an overallocation warning for my employee resource, in both tasks. Why would there be an overallocation warning here, and how can I address it? Surely in-practice the same employee can easily carry out both of these tasks, since they both require only 2 hours of his time, while spread out over a duration of 2 weeks? Perhaps I am misunderstanding something. edit: the overallocation warning remains until I alter start dates of the task until there is no overlap between them.

I have also considered adding lag to various tasks to account for waiting on the client. But lag can only be applied to the project if the task in-question is a predecessor to another task. That is not always the case with my project.

Sorry for the miscommunication. I thought that asking these very specific questions would be more efficient than one broad involved question. If you want, I can start a new topic with these latest questions.

Thanks.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Remove resource name from Gannt Bar in Project Professional 2013? nick@johansens.eu Project 1 10-16-2014 05:58 AM
[Project 2013] More accuracy with resource, unit %, and cost? How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
[Project 2013] More accuracy with resource, unit %, and cost? Need totoal cost despite project being in progress Sognamed Project 1 07-23-2013 06:06 AM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:53 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft