Old 01-23-2015, 08:00 PM
JulieS JulieS is offline Creating task view of open tasks Windows 7 64bit Creating task view of open tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't believe you are going to be able to do this through a simple filter. If you filter for incomplete tasks task 2 in your example will disappear.

It may only be possible through code. You'd need to loop through each summary task and if out if it is 100%, if not show, set a flag for all its children. The filter on the Flag.

I don't write code so I can't help much further than pseudo code. Try posting your question to :

https://social.technet.microsoft.com...ct2010custprog



Please explicitly state (as you did in this post) what version of Project. Please also be so kind as to come back here and create a post with the link to your question in the Microsoft Forum so that others may follow along.
Reply With Quote
Reply

Tags
filter, task summary



Similar Threads
Thread Thread Starter Forum Replies Last Post
Outlook Tasks 'current view'? markg2 Outlook 0 07-27-2014 08:10 AM
Scheduling Tasks to run for the duration of another task Jedra Project 3 05-12-2014 05:55 AM
Creating task view of open tasks filter 'Task name' shows all tasks Intruder Project 5 02-02-2014 07:29 AM
Creating task view of open tasks Creating Report based on 'Task Summary' and 'Sub Tasks' alijahed Project 1 02-01-2013 04:20 AM
Creating task view of open tasks Missing Tasks from Network Diagram View OTPM Project 3 11-20-2012 03:37 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:01 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft