Old 05-13-2015, 12:28 PM
JulieS JulieS is offline getting hung up on duration vs. work Windows 7 64bit getting hung up on duration vs. work Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have a two week duration task with 32 hours of work. The easiest method is to create the task with the 2 weeks duration. Change the task type to Fixed Duration. Then assign yourself and enter the 32 hours of work. Project will assign you at 40% and calculate 3.2 hours of work for 10 days.

Then when tracking you can either enter the percent complete. In your example below, you are confusing Actual Duration and Actual Work. It took you 10 days (Actual Duration) to do 32 hours of Actual Work.
Reply With Quote
 

Tags
task duration



Similar Threads
Thread Thread Starter Forum Replies Last Post
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
getting hung up on duration vs. work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
getting hung up on duration vs. work overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:44 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft