View Single Post
 
Old 05-14-2015, 02:19 PM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Again, I think we're muddling work and duration. If the resource completed the 32 hours of work in 4 days duration, then you need to update the task. I'd change it off Fixed Duration. The go to the Task Usage view, enter the 32 hours of work on the right side (Actual work) when it occurred. Make sure the remaining duration is zero.
Reply With Quote