Again, I think we're muddling work and duration. If the resource completed the 32 hours of work in 4 days duration, then you need to update the task. I'd change it off Fixed Duration. The go to the Task Usage view, enter the 32 hours of work on the right side (Actual work) when it occurred. Make sure the remaining duration is zero.
|