Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 01-06-2015, 07:38 PM
cuseman03 cuseman03 is offline getting hung up on duration vs. work Windows 8 getting hung up on duration vs. work Office 2013
Novice
getting hung up on duration vs. work
 
Join Date: Jan 2015
Posts: 2
cuseman03 is on a distinguished road
Default getting hung up on duration vs. work

Hi,



I think I have come to the right place for my problem. I have spent countless hours researching the difference between duration and work hours in Project. The way I see it, duration is the timeframe you have to complete something and work is the actual time it takes to complete it. So, if I have one week to complete a task the duration would be 40 hours but if I anticipate the actual doing of the work only taking 2 days, then work would be 16 hours. Is this right?

I always get into trouble with this when I'm building a plan. In my current example the situation is rather simple. It's a short project and I'm the only FTE, so I'm wondering if I should account for both aspects or just one? The problem as I see it is if you use duration to signify how long a task takes the problem is how do you see that within the context of having a window to complete it. Sure, you can start messing around with must complete by, etc. but I try to stay away from this.

In short, I want to be able to look at my WBS at a high level and say for each task, 1) here's how long I'm giving myself to complete the task (e.g, it can be expected within this time frame) and 2) here's how long I expect the actual task to take to complete.

Lastly, when I build my WBS should I do auto or manual based on my statement above.

Thanks,
Reply With Quote
 

Tags
task duration



Similar Threads
Thread Thread Starter Forum Replies Last Post
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
getting hung up on duration vs. work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
getting hung up on duration vs. work overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft