JulieS JulieS is offline entering duration in months Windows 7 64bit entering duration in months Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can't. You can only define "month" once in File > Options, Schedule just as you can only define "day" and "week" once. The problem is as you noted that some months have more days than others.

I suggest not using Month as a duration measure - use weeks or days.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Asked to start a pmp after three months of work done Enuhseh207 Project 3 02-18-2014 03:48 PM
events show some Calendar months, not others stoddj Outlook 0 03-28-2013 07:18 AM
entering duration in months Adding months to a Date tsindos Word 4 10-04-2011 11:20 PM
entering duration in months chart with months windseaker Excel 1 04-29-2011 11:45 PM
Setting up recurring months to skip some months etc. dwelch@ykfireprevention.c Outlook 0 11-30-2010 10:15 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft