  #4  
Old 11-20-2014, 03:27 PM
JulieS JulieS is offline HUGE BUG? Baseline Dates And Duration Windows 7 64bit HUGE BUG? Baseline Dates And Duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you save a baseline through the usual route, the "usual" Baseline fields will match the Estimated Baseline fields for auto scheduled tasks. You are correct, you can alter the data in the Baselines (including Estimated) as you always have been able to. I believe the baselines can be "locked" against alteration in the Project Server - not just client however.
Reply With Quote
 

Tags
baseline fields



Similar Threads
Thread Thread Starter Forum Replies Last Post
HUGE BUG? Baseline Dates And Duration Amending dates and recalculating duration seanpears99 Project 1 12-03-2012 07:18 AM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM
HUGE BUG? Baseline Dates And Duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
HUGE BUG? Baseline Dates And Duration baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
HUGE BUG? Baseline Dates And Duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:00 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft