I want to show cum scheduled work to the status date for each task in a table column to help my cost control person understand the BCWS values that MSP calculates. I understand that this is displayed in the timescaled task usage field. Therefore it must be calculated internally by summing the timescaled scheduled work to the status date, but it is not offered as a custom field in MSP 2003. It appears that it is in later versions, and I am wondering if there is a formula I could use to customize a field to display in a column.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - entering work hours at a monthly level aj18 Project 4 05-26-2014 10:32 AM
Formula for cum work in Project 2003 Excel 2010- What does this formula mean and how does it work dangoodwin1 Excel 1 10-31-2012 09:18 PM
formula to work from data column masterdineen Excel 16 08-09-2012 07:52 AM
How to show Vacations at the Bottom of Work Schedule in Office Project 2007? Rahmat_uk20 Project 3 06-08-2012 01:53 PM
Formula for cum work in Project 2003 Implementing excel formula in project nawab35 Project 6 08-04-2011 05:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:42 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft