![]() |
#3
|
|||
|
|||
![]()
I want to show cum scheduled work to the status date for each task in a table column to help my cost control person understand the BCWS values that MSP calculates. I understand that this is displayed in the timescaled task usage field. Therefore it must be calculated internally by summing the timescaled scheduled work to the status date, but it is not offered as a custom field in MSP 2003. It appears that it is in later versions, and I am wondering if there is a formula I could use to customize a field to display in a column.
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project 2013 - entering work hours at a monthly level | aj18 | Project | 4 | 05-26-2014 10:32 AM |
![]() |
dangoodwin1 | Excel | 1 | 10-31-2012 09:18 PM |
formula to work from data column | masterdineen | Excel | 16 | 08-09-2012 07:52 AM |
How to show Vacations at the Bottom of Work Schedule in Office Project 2007? | Rahmat_uk20 | Project | 3 | 06-08-2012 01:53 PM |
![]() |
nawab35 | Project | 6 | 08-04-2011 05:45 AM |