JulieS JulieS is offline Formula for cum work in Project 2003 Windows 7 64bit Formula for cum work in Project 2003 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default


Cumulative work is a timescaled field. What are you trying to accomplish? If you want to know how much work has been performed, that is Actual Work. If you want to know how much work is left, that is remaining work. If you want to know how much work in total was planned, that's baseline work. All of those fields are also visible in the Project Summary row to roll up all the values for the entire project.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - entering work hours at a monthly level aj18 Project 4 05-26-2014 10:32 AM
Formula for cum work in Project 2003 Excel 2010- What does this formula mean and how does it work dangoodwin1 Excel 1 10-31-2012 09:18 PM
formula to work from data column masterdineen Excel 16 08-09-2012 07:52 AM
How to show Vacations at the Bottom of Work Schedule in Office Project 2007? Rahmat_uk20 Project 3 06-08-2012 01:53 PM
Formula for cum work in Project 2003 Implementing excel formula in project nawab35 Project 6 08-04-2011 05:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:09 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft