Hi Anne,

Work does equal duration if you have 1 resource assigned at 100%. You can add the work field and copy/paste the duration value into the work field if you want to do some very high level planning. However, you may have a scenario where you want the task duration (from start to finish) to show a longer period of time than you estimate the work. For example, you might say it takes a week in duration to accomplish the task - but it is really only about 25 hours of effort)

I do want to caution if you want to get more involved in Project on a deeper level - usually manually adding work without resources is on the "don't" list.

You can add your tasks, select multiple and then indent. The task above becomes the summary.
Attached Images
File Type: jpg ann.jpg (150.1 KB, 17 views)
Reply With Quote
 

Tags
summary tasks



Similar Threads
Thread Thread Starter Forum Replies Last Post
Getting started... Page footers have started ravl13 Word 3 11-21-2013 12:31 PM
Getting started... Auto move un-started tasks myoung Project 1 01-29-2013 04:10 PM
Internet Explorer unresponsive when started from vba ppg PowerPoint 0 12-17-2012 08:13 AM
Getting started... Microsoft Office 2010 getting started kate Office 2 05-15-2012 08:54 PM
Need Help Getting Started, Please. Thanks ChunkyZergling Outlook 1 04-24-2009 07:38 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:11 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft