#1
|
|||
|
|||
|
I'm guessing you mean the total slack returns to zero? FNLT constraints (as long as they are not violated) will not add positive total slack. You are merely saying the task needs to finish by a certain date - but it can finish earlier. If you wish to add total slack - set a must finish on. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
Start No Later Than constraint
|
EC37 | Project | 3 | 05-13-2014 10:13 AM |
Changing Actual Finish dates changes original Finish dates
|
SomewhereinTX | Project | 3 | 12-20-2013 10:25 AM |
activities getting constraint dates vs starting as soon as possible
|
ketanco | Project | 1 | 08-30-2012 05:27 AM |
Update Progress breaks with constraint
|
benwimpory | Project | 1 | 03-14-2012 08:44 AM |