#8
|
|||
|
|||
![]()
to see a cost distribution by time you can first assign fixed costs to the item summary tasks as you wrote in your original post.
then go to task view. select cummulative cost. you will see a cumulative cost distribution by time and then you can copy paste these to excel and draw a nice graph |
|
![]() |
||||