![]() |
|
![]() |
|
Thread Tools | Display Modes |
#1
|
|||
|
|||
![]()
Hello -
I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view. ACWP for 9/8/2014 ![]() (Matches values shown in Gantt view and in a column chart in the report.) ![]() ![]() ![]() The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP. Any idea why I am seeing this seeming inconsistency? Thanks! |
#2
|
|||
|
|||
![]() |
#3
|
|||
|
|||
![]()
Thanks Julie. I replied with comments in the same thread on Stack Exchange. For quick reference for other readers, my response is below:
-------------------------------------------------------------------------------------- Thanks Julie - I appreciate it. I tried a couple of different things based on your post. First, I removed the fixed cost entry for the task in question, and instead created a cost resource (with a per unit rate of $80,000). I assigned the cost resource to the task with an estimated usage of 1 unit, then re-baselined that task (with roll-up to summary tasks.) When I did this, for some reason, the Planned Value (BCWS) would not pick up the $80,000 cost, even when I set the status date well beyond the time for which I entered the actual usage. Neither did the Earned Value (BCWP). However, the ACWP did pick up the $80,000 cost. So it still left me with very large artificial variances. In the end, I simply decided to remove that element from the schedule entirely, since it has no potential to deviate from the planned value, and I am more concerned, at this time, with tracking the progress of the actual work effort. In addition, upon further reflection, I decided that the magnitude of the $80,000 cost was so large in proportion to the relatively small weekly labor costs of $3K-$4K that a positive schedule variance for that task (if completed ahead of schedule) would severely obscure any negative variances in the labor tasks when the project was viewed as a whole. (At least until the original planned date of the $80,000 task had passed.) This was an additional reason I chose to drop it. This results in an overall cost picture that is not entirely accurate since it doesn't include the $80,000, but it allows me to more effectively track the work being done on the project. And in case anyone is wondering, this technique is being used on a small project as a "work out the kinks" exercise before being applied to larger efforts. That is why I am spending so much monitoring effort on a set of tasks that is relatively small. |
#4
|
|||
|
|||
![]()
Hi Bill.
Replied at Stack Exchange. |
![]() |
Tags |
acwp |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Cash flow reports in MS Project 2013 | sansrini18 | Project | 3 | 09-09-2013 06:06 AM |
column chart prob | sturner333 | Excel | 0 | 01-09-2013 12:29 PM |
Column Chart Average | blaqsheep | Excel | 0 | 02-07-2012 07:04 PM |
MS Project Resource Chart | fherbert | PowerPoint | 0 | 09-09-2010 12:20 PM |
Bar chart in Project 2010. | aligahk06 | Project | 0 | 07-04-2010 07:37 AM |