When you create a resource, each resource has his/her own calendar that is, by default, a copy of the project calendar. You use the resource's calendar to record differences (vacation, different working hours) from the base calendar. You cannot remove the calendar without removing the resource. Again, what is the problem with showing the resource's calendar in the Change Working Time command?
|
|
![]() |
||||