JulieS JulieS is offline Fixed end but variable start (and duration) Windows 7 64bit Fixed end but variable start (and duration) Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid there isn't a direct way to accomplish all of the needs.
You can set a deadline on the Variable task.
You can set a Start No Later Than constraint on the variable task.

You can make the variable task a successor of the Jan tasks however a F to S relationship is always the later of the two. So if the first task moves to past Feb 1, you'll need to manually remove the link to the Jan task and re-link to the Feb 1 task.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed end but variable start (and duration) How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
Fixed end but variable start (and duration) Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Fixed end but variable start (and duration) How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft