Default

The resource leveling command is used to resolve resource overallocations. It is not a resource optimization tool. If the resources are not fully utilized, assign them at their maximum units - then at least if the schedule is leveled they will be fully assigned when they are assigned.
You may also want to allow the leveling command to level individual assignments - that way if one resource is not overallocated s/he can work on the task independent of other works.
Regarding gaps - there really isn't any way around that. If Resource A is waiting on an output from a task that Resource B is working on - there may be times when A is just waiting without other tasks.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Assignment Summary Line Not Adding Up Correctly PeteS Project 2 07-18-2014 06:24 AM
Resource assignment with resource calendars Over-allocated resource - resource holiday scott.hannaford Project 1 10-21-2013 05:32 AM
resource issue safaa Project 1 11-20-2012 05:41 AM
Resource Calendars caz46 Project 0 02-12-2011 05:31 AM
Resource use on tasks Proj03 Project 0 01-24-2011 01:40 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft