Old 03-30-2015, 05:56 PM
patrickd123 patrickd123 is offline How to Input Actual Overtime Work Windows XP How to Input Actual Overtime Work Office 2003
Novice
 
Join Date: Dec 2011
Posts: 21
patrickd123 is on a distinguished road
Default

Well you were right. I saw further down the list other task that had work on them for the same resource, therefore it was not the actual causing the overallocation.
Thanks!
Reply With Quote
 

Tags
actual, overtime, projet



Similar Threads
Thread Thread Starter Forum Replies Last Post
Actual working hours per day climbatron Project 2 12-17-2015 03:13 PM
How to Input Actual Overtime Work about usage of Timesheet and Overtime in Project server Hyung-Ho Yoon Project 3 07-15-2014 09:13 AM
Actual work in the future joday48 Project 3 07-06-2012 06:00 AM
How to Input Actual Overtime Work overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:43 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft