Yes, that is correct. Work = Actual Work when the task is tracked. If you want to know how much work you originally planned - save a baseline before tracking. Then you can see the difference in Baseline Work (16 hours) and Actual Work (8 regular 4 OT).
Reply With Quote
 

Tags
actual, overtime, projet



Similar Threads
Thread Thread Starter Forum Replies Last Post
Actual working hours per day climbatron Project 2 12-17-2015 03:13 PM
How to Input Actual Overtime Work about usage of Timesheet and Overtime in Project server Hyung-Ho Yoon Project 3 07-15-2014 09:13 AM
Actual work in the future joday48 Project 3 07-06-2012 06:00 AM
How to Input Actual Overtime Work overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft