Hi Julie, so I've entered 8h in Actual Work and 4h in Actual Overtime Work (so that the total will be 12h), but MS Project automatically converts the Work and Actual Work to 12h. Is this supposed to be the correct behaviour? What is the difference between Work and Actual Work?
|