#1
|
|||
|
|||
![]()
The values have been recalculated and show in the Peak field. Apply the Task Usage or Resource Usage view and add the Peak value to see what is really going on.
See: http://blogs.msdn.com/b/project/arch...ject-2010.aspx for an explanation of the change. |
#2
|
|||
|
|||
![]()
Dear JulieS,
Thanks so much for the link to the article. It cleared up my question and gave me a better understanding of Project 2010. Louis |
![]() |
|
![]() |
||||