#1
|
|||
|
|||
Multiple resources on one task
Hi all I'm a little rusty. I'm working in 2010. I have been given the durations (in days) that tasks will take. I have multiple resources, all of whom will be working on the same tasks, all assigned units will differ, example, resource A will spend 60%, B will spend 20% and C will spend 20%. Apparently each resource with have a different number of effective hours per day. How should I handle this in the schedule? thanks JD |
#2
|
|||
|
|||
Hi
Can anyone tell me if i can have multiple resources with different resource calendars assigned to the same tasks? Thanks Jo |
#3
|
|||
|
|||
Yes, of course. When you create resources, each has his/her own calendar. If Bob only works 6 hours per day - then change his calendar. However, if you want to say Bob can only produce 6 hours per day out of 8 hours - then don't change his calendar, set his max units at 75%. Then, when you assign Bob to the task, he will be assigned at 75% - the work for him will be calculated at 75% of duration. Or, you can enter his work and Project will calculate duration.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Assign different resources with different colors to the same task | Shir | Project | 9 | 05-05-2017 12:29 PM |
Allocating multiple resources to a task and splitting the hours | pptdgc | Project | 1 | 07-22-2014 03:45 AM |
Task types with no Resources assigned | mtaylor | Project | 1 | 05-24-2014 12:37 PM |
excel cannot complete this task with available resources - vlookup | Taisho | Excel | 4 | 01-27-2012 03:09 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |