#4
|
|||
|
|||
![]()
You create calendars in Project > Change working time > Create new calendar. See:
http://office.microsoft.com/en-us/pr...102809468.aspx for details on changing the work weeks to something other than 8-12, 1-5. |
|
![]() |
||||