#2
|
|||
|
|||
|
What kind of field have you used for the custom formula? What error are you seeing? Are you using autoscheduled or manually scheduled tasks?
I used your formula in a number field and it showed the correct value. Tested in Project 2010 with SP-2 and the latest cumulative update installed. |
|
|