#16
|
|||
|
|||
Problem has resolved
|
#17
|
|||
|
|||
Now I want only 5th Saturday off OR as a working day in whole year to perform additional activity of project team.
File is attached herewith. There is no option of 5th Saturday, if we select the last Saturday, it applies on every month. Regards, Arif |
#18
|
|||
|
|||
Which is it - every fifth Saturday off? Every fifth Saturday is a working day?
Don't go with the Monthly setting - try the weekly - every fifth Saturday. |
#19
|
|||
|
|||
Hi Miss Julie,
This option applies on every 5th Saturday, and might be come on 1st week of next month. I want this change only on particular month, in which 5th Saturday comes (i.e January-2015, March-2015) Files are attached Regards. Arif |
#20
|
|||
|
|||
So, you only get the Saturday off if there are 5 Saturdays in the calendar month? That will need to be done manually as you have done with January and May in 2015.
|
#21
|
|||
|
|||
Thanks alot
|
#22
|
|||
|
|||
You're welcome
|
|