#1
|
|||
|
|||
|
The fact that the finish of B can be delayed by one day (currently) is not reflected anywhere directly in this release. G is the driving predecessor and you can see that in the task inspector for Task D. Task B is not listed in the inspector window as it is not currently driving D. |
|
|
|