Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 06-13-2014, 10:34 AM
ketanco ketanco is offline writing task logic and task information box Windows 7 64bit writing task logic and task information box Office 2010 64bit
Expert
writing task logic and task information box
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default writing task logic and task information box


hello
i changed from ms project 2007 to 2010 here and trying to get used to it..

in ms project 2010 how do you manually write the logical relationships from keyboard? i know that when we go onto the predecessor or successor cell we do it but once we do it there is no way of editing the cell it seems. we have to write everything from beginning if we want to make a change

also when i bring the task information box, there is no tab for successor. only predecessor, general, resources, advanced ... fields but no field for successor,.

also in ms project 2007 i was able to enter the logic not only from the cell itself but when i went into that call there was a horizontal bar at the top and i was able to enter from there too. it is not here now
Reply With Quote
  #2  
Old 06-15-2014, 09:02 AM
JulieS JulieS is offline writing task logic and task information box Windows 7 64bit writing task logic and task information box Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
in ms project 2010 how do you manually write the logical relationships from keyboard? i know that when we go onto the predecessor or successor cell we do it but once we do it there is no way of editing the cell it seems. we have to write everything from beginning if we want to make a change.
F2 is the edit key in all releases of Project, including Project 2010. Click in the predecessor or successor field and press F2 to enter the edit mode.

Quote:
also when i bring the task information box, there is no tab for successor. only predecessor, general, resources, advanced ... fields but no field for successor,.
The Task Information dialog is the same as it was in 2007. You can display predecessor and success information in the Task form in the lower part of a split screen.

Quote:
also in ms project 2007 i was able to enter the logic not only from the cell itself but when i went into that call there was a horizontal bar at the top and i was able to enter from there too. it is not here now
You may turn in the Edit bar in File > Options, Display.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
writing task logic and task information box Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
writing task logic and task information box Task not rolling up after single task was baselined Hwlr Project 1 06-05-2013 03:43 PM
writing task logic and task information box Task Information Dialog Box Plas Project 3 10-21-2012 06:30 AM
writing task logic and task information box seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:50 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft