#1
|
|||
|
|||
![]()
If a have a huge project and I finished assigning ressources to it, how can I see or be notified that a task in the whole group his only partially staffed, let's say at 50%?
|
#2
|
|||
|
|||
![]()
Found it! So, for the record, Resource>View>Resource Usage and look at the line Unassigned
Also, another question I had and found a way: How can I most efficiently see where I have bandwidth? Answer: Resource>View>Resource Usage, right click on table view, select Remaining availability instead of work and bingo! |
#3
|
|||
|
|||
![]()
Thanks for posting the resolution, Patrick.
|
![]() |
|
![]() |
||||