In short, you can't. Project are constrained by 3 factors - Time, Cost, and Quality. Without some understanding of resource availability and work estimates, you cannot create a schedule. What will take ten resources one week will take one resource ten weeks.
I'm sorry to say - you appear to have been set up for failure. |
|
![]() |
||||