Old 06-08-2014, 08:39 AM
JulieS JulieS is offline Issue regarding calculating costs of rental equipment Windows 7 64bit Issue regarding calculating costs of rental equipment Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You may assign material resources at a specific unit per day.
  1. Split the screen to show the Task Form in the lower pane.
  2. Select the Crane resource from the Resource Name list.
  3. In the Units field type 1/d to assign the crane at 1 crane per day.

If the duration of the task increases or decreases, Project will calculate the correct usage of the crane.

I hope this helps.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Issue regarding calculating costs of rental equipment a rental period in between two activities ketanco Project 5 10-21-2012 06:28 AM
assiging equipment as resource ketanco Project 3 06-10-2012 03:32 AM
Issue regarding calculating costs of rental equipment Non-recurring costs (NRE) Trigger Project 1 04-26-2012 03:41 PM
Issue regarding calculating costs of rental equipment Managing equipment and person operating equipment ProfessorGilligan1 Project 1 04-12-2012 12:29 PM
Issue regarding calculating costs of rental equipment entering lump sum costs ketanco Project 1 12-24-2011 12:56 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:48 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft