You may assign material resources at a specific unit per day.
  1. Split the screen to show the Task Form in the lower pane.
  2. Select the Crane resource from the Resource Name list.
  3. In the Units field type 1/d to assign the crane at 1 crane per day.

If the duration of the task increases or decreases, Project will calculate the correct usage of the crane.

I hope this helps.