You may assign material resources at a specific unit per day.
- Split the screen to show the Task Form in the lower pane.
- Select the Crane resource from the Resource Name list.
- In the Units field type 1/d to assign the crane at 1 crane per day.
If the duration of the task increases or decreases, Project will calculate the correct usage of the crane.
I hope this helps.