#1
|
|||
|
|||
![]()
In project 2010, I want to see only the tasks that happening in the next 3 months. For example tasks that happening between 1/6/14 to 1/9/14: the task can start before 1/6/14 and end after 1/9/14. or - start after 1/6/14 and end before 1/9/14 etc.
Please Your help, Thanks in advance |
#2
|
|||
|
|||
![]()
Hi
You can use the Date Range filter for this. Click on the View tab followed by clicking on the little arrow next to the Filter drowdown box and choose Date Range... Hope this helps. Tony |
![]() |