Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 05-27-2014, 07:38 AM
JulieS JulieS is offline Once you have a % complete does it always lock in the dates? Windows 7 64bit Once you have a % complete does it always lock in the dates? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

When you add progress to a task, Project enters an Actual Start date. If you wish to control when a task started, show the Tracking Table and specify Actual Start and % complete.

If you want to set the tasks as milestones, first enter the zero duration then enter Actual Start and 100% complete.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Once you have a % complete does it always lock in the dates? Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
Any way to lock tab stops ctenanthe Word 1 01-31-2013 11:20 PM
Once you have a % complete does it always lock in the dates? complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
Num Lock ERROR judicial85 Excel 6 05-04-2012 10:43 AM
Once you have a % complete does it always lock in the dates? % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:19 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft