Once you have a % complete does it always lock in the dates?
I am using a project plan from an artifact folder set up by my work group. This project plan "master" is set as it should be for a brand new project. All durations are set up as though nothing is complete and % complete is at "0" also as it should be.
My problem is the project we are starting already has many of the tasks 100% complete so I prefer to set these tasks to "0" days duration and 100% complete to get an early estimate of how long the project will take. However once I set any % complete it locks the start and end date in place and I have to then go back, set the % complete to "0%" change the duration time and then go back again and change the % complete to 100%.
Is there a way to change a setting so I can change durations and % complete separately so it doesn't lock in start and end dates?
|