![]() |
#3
|
|||
|
|||
![]()
Thanks Julie,
I was doing things the wrong way around! The plan is for a project estimated to start much later this year so at present I'm anticipating a start date change (which will then drive a change to the end date) but with the duration remaining the same. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Auto scheduling issue - longest task first? | Project_64 | Project | 3 | 01-25-2016 01:14 PM |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
![]() |
seanpears99 | Project | 1 | 03-08-2013 08:58 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Outlook issue--task list | Renee Arena | Office | 0 | 01-23-2006 11:09 AM |