#1
|
|||
|
|||
|
Add the task to the schedule, and set it as fixed work. Assign the resource and specify the number of work hours. Then do the paste link to the Project start and Project Finish. However - are you sure it's fixed work? If the duration of the project increases, shouldn't the work increase as well?
|
|
#2
|
|||
|
|||
|
Thanks Julie,
I was doing things the wrong way around! The plan is for a project estimated to start much later this year so at present I'm anticipating a start date change (which will then drive a change to the end date) but with the duration remaining the same. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Auto scheduling issue - longest task first? | Project_64 | Project | 3 | 01-25-2016 01:14 PM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly
|
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Use VBA to create Hammock Tasks
|
seanpears99 | Project | 1 | 03-08-2013 08:58 AM |
| how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
| Outlook issue--task list | Renee Arena | Office | 0 | 01-23-2006 11:09 AM |