SaraJH SaraJH is offline Hammock task issue Windows 7 64bit Hammock task issue Office 2010 64bit
Novice
Hammock task issue
 
Join Date: May 2014
Posts: 2
SaraJH is on a distinguished road
Default Hammock task issue


Hi,

What a fantastic site! Hopefully you will be able to help me with a problem I have in MS Project.

I have a hammock task in my plan linked to the Project Start milestone and Project Complete milestone. The Hammock task is set to Fixed Work.

When I assign 90 days work to this task the start date moves away from project start (project duration is 225 days). I thought that the purpose of hammock tasks was that they didn't behave like this or am I doing something woring?

Many Thanks
Sara.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto scheduling issue - longest task first? Project_64 Project 3 01-25-2016 01:14 PM
Hammock task issue Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Hammock task issue Use VBA to create Hammock Tasks seanpears99 Project 1 03-08-2013 08:58 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
Outlook issue--task list Renee Arena Office 0 01-23-2006 11:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft