![]() I assigned the 24 hour calendar to some of the activities. before assigning, I had entered their duration when they had standard calendar. but now for example even if it says 2 day duration, it shows the start and finish the same day, because of 24 hour calendar so it doesnt make sense. how can I show durations of those activities properly? so when i say 2 days for that, I mean 2 days based on 24 hour calendar now. i also tried entering hours to work column but when i do that nothing change for duration |
#2
|
|||
|
|||
![]()
You can only define the definition of a "day" once per project file. My suggestion is to assign resources and specify their work. 24 hours of work on the standard calendar will take 3 working days from beginning to end. The same task assigned the 24 hours calendar will start and finish in a 24 hour period.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Differentiate certain activities from hypotetical activities in gantt chart | Serena | Project | 1 | 02-24-2014 10:47 AM |
events show some Calendar months, not others | stoddj | Outlook | 0 | 03-28-2013 07:18 AM |
![]() |
Sneezy | Outlook | 1 | 12-12-2012 05:35 AM |
![]() |
ketanco | Project | 5 | 05-22-2012 01:04 PM |
![]() |
Lin | Outlook | 1 | 07-26-2010 05:34 AM |