#1
|
|||
|
|||
![]()
I have sevaral activities using 24 hour calendar. The first activity must start friday afternoon and starting that point it is a 24 hour calendar job (befor ethis it is normal calendar). Because the whole 24 calendar portion will last only 3 days, over a long weekend, it must start on friday afternoon and finish Tuesday morning. (from 8/29 afternoon to 9/2 early morning)
First of all is it possible to show that it starts 8/29 afternoon? and then the first tasks finish saturday afternoon and finish monday morning... then next set of tasks will take another 24 hours. so i must be able to divide the units to hours for that portion I guess, but the rest of the schedule before is in days units as usual. so is this possible? |
#2
|
|||
|
|||
![]()
You may turn on the display of time to show when tasks begin and end. For Project 2007, Tools > Options, General tab.
|
#3
|
|||
|
|||
![]()
on MS project 2007 I couldnt see this
|
#4
|
|||
|
|||
![]()
Sorry, View tab.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
![]() |
Hwlr | Project | 1 | 06-05-2013 03:43 PM |
one-half space? | markbh | Word | 2 | 07-05-2012 10:08 PM |
Half Page breaks | Meltron3030 | Word | 2 | 02-22-2012 10:34 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |