Hi,
Pls let me if the below if possible. I have a task starting from 1st May; I need 4 resources for it. I have 1 resource available from 1st May, 1 from 5th May, another from 7th May and 1 from 10th. Can you pls tell me if there is a way to assign these resources to the task, such that they finish the first task and then start this one. If I put predecessors, then the task starts from 10th May, cosnidering the 4th resource. |
|
![]() |
||||